Michigan Avenue Area Developments


Attached is a drawing showing the locations of planned work in the Streeterville area.  The light green lines inside the shaded areas are the proposed new gas mains.

This work began Thursday, March 12 with all locations, except St. Clair, scheduled to be completed by April 24.  Once this preliminary work is completed, we will be in St. Clair with a scheduled completion date of July 1.

This project is mainly installing new gas main.  There will be several services that will have to be transferred to new main.  We will work with those customers to minimize any disruption of service.


If you have any questions or need additional information, please call:  Rodney Looney/ Manager – Construction/ (773)542-7840