Attached is a drawing showing the
locations of planned work in the Streeterville area. The light green lines
inside the shaded areas are the proposed new gas
mains.
This work began Thursday, March 12 with all
locations, except St. Clair, scheduled to be completed by April
24. Once this preliminary work is completed, we will be in St.
Clair with a scheduled completion date of July
1.
This project is mainly installing new gas main. There will be several services that will have to be transferred to new main. We will work with those customers to minimize any disruption of service.
If you have any questions or need
additional information, please call: